MN DOT reminds you that lane closures west of Alexandria on I 94 will start tomorrow, July 11th. Traffic will be reduced to single lane usage as traffic control devices and crossovers are installed. The lanes should be fully open again by November.
Project details

In 2023, the Minnesota Department of Transportation will complete a project to resurface the westbound lanes on Interstate 94 west of Alexandria. The project is located near Highway 114, between mile posts 96 and 100.
Key project elements
- Concrete overlay
Upcoming traffic impacts
- Lane closures begin July 11
- Westbound lanes close at the end of July, with crossovers/head-to-head traffic on eastbound lanes until October